Initiative Title | LED lighting change out for Middletown Campus |
Submitted in Previous Year(s) | 2018 |
Critical Information, Notes, Justification, Rationale | Replace lighting with LED will save excessive energy costs. |
Consequences of this initiative not being funded | The consequence of this initiative not being funded would be higher energy costs for the College. |
Department Goals | |
Programs | |
Locations | Main Campus |
Estimated Completion Date | |
Will this initiative span multiple budget years? | Yes |
Importance | Medium |
Funding Source | Request for Prioritization |
Created | 11/07/2019 9:38 am |
Updated | 11/07/2019 9:38 am |
Institutional Goals
Goal |
How will the initiative support this institutional goal? |
- COLLEGE GOALS as of 2011
- 6. To build and maintain safe, accessible and sustainable facilities that support the learning environment.
|
Cost savings |
Action Steps
Action Step |
Responsible Party |
Order |
Purchase material and change out the lighting fixtures. |
Maintenance Manager/Assistant Maintenance Manager |
1 |
Expected Outcomes
Outcome |
Order |
Saving money on electrical costs. Longer lamp life which provides better lighting for security purposes. |
1 |
Assessment Methods
Method |
Description |
Other Method |
Responsible Party |
Other |
Enter other assessment method |
Visual Inspection |
Maintenance Manager/Assistant Maintenance Manager |
Resources
INITIAL YEAR COST: |
$200,000.00 |
RECURRING COST: |
$0.00 |
Equipment
Need |
Cost (Initial/Recurring) |
Supporting Departments |
TOTAL: |
$0.00 / $0.00 |
|
Facility
Need |
Cost (Initial/Recurring) |
Supporting Departments |
TOTAL: |
$0.00 / $0.00 |
|
Supply
Need |
Cost (Initial/Recurring) |
Supporting Departments |
Campus LED lighting fixtures |
$200000.00
|
|
TOTAL: |
$200,000.00 / $0.00 |
|
Staffing
Need |
Cost (Initial/Recurring) |
Supporting Departments |
TOTAL: |
$0.00 / $0.00 |
|
Training
Need |
Cost (Initial/Recurring) |
Supporting Departments |
TOTAL: |
$0.00 / $0.00 |
|
Marketing
Need |
Cost (Initial/Recurring) |
Supporting Departments |
TOTAL: |
$0.00 / $0.00 |
|
Other
Need |
Cost (Initial/Recurring) |
Supporting Departments |
TOTAL: |
$0.00 / $0.00 |
|
Prioritization
This is initiative is ready for prioritization.
Assessment
Date | Department Name | Status | Cost to Date | Funding Source | |
No results found. |