Initiative Title | 29 new Computers for BT 121 |
---|---|
Submitted in Previous Year(s) | No |
Critical Information, Notes, Justification, Rationale | Given the every 3 year technology replacement plan, these computers are now 4 years old. The purpose for waiting the additional year was to allow no more than 2 rooms at a time within the department requiring upgrades at any one time. As stated in the reason last year for upgrading furniture in this room, this is an excellant room for training. It is also a rather large room and could accomodate more machines for this purpose. This room could accomodate 4 rows of 4 on one side and 4 rows of 3 on the other side. This would hold 28 computers, plus one for the instructor station |
Consequences of this initiative not being funded | This equipment is now well outdated. Upgraded software would be most likely unable to run on these machines. |
Department Goals | |
Programs | AAS CIS, AAS Electrical Engineering Technology, AAS Information Technology, Computerized Learning Laboratory |
Locations | |
Estimated Completion Date | 01/11/2010 |
Will this initiative span multiple budget years? | No |
Importance | Low |
Funding Source | Request for Prioritization |
Created | 06/17/2013 5:03 pm |
Updated | 06/17/2013 5:03 pm |
Goal | How will the initiative support this institutional goal? |
---|---|
|
|
|
|
|
|
|
Action Step | Responsible Party | Order |
---|---|---|
Order Computers | Department Chair | 1 |
Install Software | IT Department | 2 |
Install computers in room | IT Department | 3 |
Outcome | Order |
---|---|
Updated computers on a 3 year replacement cycle | 1 |
Method | Description | Other Method | Responsible Party |
---|
INITIAL YEAR COST: | $47,000.00 |
---|---|
RECURRING COST: | $0.00 |
Need | Cost (Initial/Recurring) | Supporting Departments | |
---|---|---|---|
29 Computers for BT 121 | $47000.00 |
|
|
TOTAL: | $47,000.00 / $0.00 |
Need | Cost (Initial/Recurring) | Supporting Departments | |
---|---|---|---|
TOTAL: | $0.00 / $0.00 |
Need | Cost (Initial/Recurring) | Supporting Departments | |
---|---|---|---|
TOTAL: | $0.00 / $0.00 |
Need | Cost (Initial/Recurring) | Supporting Departments | |
---|---|---|---|
TOTAL: | $0.00 / $0.00 |
Need | Cost (Initial/Recurring) | Supporting Departments | |
---|---|---|---|
TOTAL: | $0.00 / $0.00 |
Need | Cost (Initial/Recurring) | Supporting Departments | |
---|---|---|---|
TOTAL: | $0.00 / $0.00 |
Need | Cost (Initial/Recurring) | Supporting Departments | |
---|---|---|---|
Installation of Computers | $0.00 |
|
|
TOTAL: | $0.00 / $0.00 |
Date | Department Name | Status | Cost to Date | Funding Source | |
---|---|---|---|---|---|
No results found. |