Classroom Technology Replacement



Initiative TitleClassroom Technology Replacement
Submitted in Previous Year(s)No
Critical Information, Notes, Justification, Rationale

There is a lifecycle and expected End of Life (EOL) for all technology equipment.  Our projectors and large panel displays are no different.  In order to maintain a proper working and learning environment on campus, we must proactively replace aging display technology in classrooms and conference spaces.  We are planning on beginning the replacement of the classroom and conference room technology in thirty-four rooms per year.

Consequences of this initiative not being funded

If this initiative is not appropriately funded, we will continue to see the projectors and large panel displays on campus break down and become unusable.  

Department GoalsUpdate Technology
Programs
Locations
Estimated Completion Date
Will this initiative span multiple budget years?Yes
ImportanceHigh
Funding SourceRequest for Prioritization
Created02/10/2023 2:13 pm
Updated03/27/2023 11:00 am

Institutional Goals

Goal How will the initiative support this institutional goal?
With consistently updated equipment, the student experience will be enhanced.

Action Steps

Action Step Responsible Party Order
Assess the rooms slated to be replaced and discuss options with stakeholders CIO 1
Purchase requisite hardware CIO 2
Install Hardware in Rooms Technology Services Team 3

Expected Outcomes

Outcome Order
Reliable presentation hardware across campus 1

Assessment Methods

Method Description Other Method Responsible Party
Observations Information can be collected while observing “events” (including, sponsored activities, student {office staff} sessions, etc.) in the natural setting. Observation can provide information on student behaviors and attitudes. Campus Community

Resources

INITIAL YEAR COST: $153,816.00
RECURRING COST: $153,816.00

Equipment

Need Cost (Initial/Recurring) Supporting Departments
Display and mounting hardware $153816.00 / 153816.00 (1st year)
  • Information Technology, CIO Office
TOTAL: $153,816.00 / $153,816.00

Facility

Need Cost (Initial/Recurring) Supporting Departments
TOTAL: $0.00 / $0.00

Supply

Need Cost (Initial/Recurring) Supporting Departments
TOTAL: $0.00 / $0.00

Staffing

Need Cost (Initial/Recurring) Supporting Departments
TOTAL: $0.00 / $0.00

Training

Need Cost (Initial/Recurring) Supporting Departments
TOTAL: $0.00 / $0.00

Marketing

Need Cost (Initial/Recurring) Supporting Departments
TOTAL: $0.00 / $0.00

Other

Need Cost (Initial/Recurring) Supporting Departments
TOTAL: $0.00 / $0.00

Prioritization

Level 5 Level 4 Level 3 Level 2 Level 1 Initiative Title Department



3

Classroom Technology Replacement
$153,816.00 / $153,816.00
Information Technology, CIO Office

Prioritization Notes

Level 3 (Administration and Finance, VP Office)

Capital Budget - IT replacement plan

Assessment

DateDepartment NameStatusCost to DateFunding Source 
No results found.