Hire adequate staff and materials needed to complete projects for Newburgh Campus



Initiative TitleHire adequate staff and materials needed to complete projects for Newburgh Campus
Submitted in Previous Year(s)2018
Critical Information, Notes, Justification, Rationale

Need one laborer and one auxiliary position to be filled to complete jobs in a timely manner. 

Consequences of this initiative not being funded

Without adequate amount of staff, work orders, projects and preventative maintenance plan not being completed in a timely manner. 

Department Goals
Programs
LocationsNewburgh Campus
Estimated Completion Date
Will this initiative span multiple budget years?Yes
ImportanceHigh
Funding SourceRequest for Prioritization
Created11/08/2018 11:05 am
Updated01/15/2019 2:11 pm

Institutional Goals

Goal How will the initiative support this institutional goal?
To build and maintain safe, accessible and sustainable facilities that support the learning environment.

Action Steps

Action Step Responsible Party Order
Submit a justification form to responsible party Director of Faciliities 1

Expected Outcomes

Outcome Order
Projects, work orders and preventative maintenance plans would be completed in a timely manner. 1

Assessment Methods

Method Description Other Method Responsible Party
Tracking Usage of programs, services, participation can be tracked; demographic information may also be able to be collected. Assistant Maintenance Manager/Maintenance Manager

Resources

INITIAL YEAR COST: $81,700.00
RECURRING COST: $40,200.00

Equipment

Need Cost (Initial/Recurring) Supporting Departments
Maintenance Truck $40000.00
  • Maintenance
TOTAL: $40,000.00 / $0.00

Facility

Need Cost (Initial/Recurring) Supporting Departments
TOTAL: $0.00 / $0.00

Supply

Need Cost (Initial/Recurring) Supporting Departments
100 yards of mulch $3000.00 / 3000.00 (1st year)
  • Maintenance
TOTAL: $3,000.00 / $3,000.00

Staffing

Need Cost (Initial/Recurring) Supporting Departments
One full time laborer and one auxiliary postion $37200.00 / 37200.00 (1st year)
  • Maintenance
TOTAL: $37,200.00 / $37,200.00

Training

Need Cost (Initial/Recurring) Supporting Departments
Protective Equipment, Ladder Safety and Safe & efficient operation of power tools $1500.00
  • Maintenance
TOTAL: $1,500.00 / $0.00

Marketing

Need Cost (Initial/Recurring) Supporting Departments
TOTAL: $0.00 / $0.00

Other

Need Cost (Initial/Recurring) Supporting Departments
TOTAL: $0.00 / $0.00

Prioritization

Level 5 Level 4 Level 3 Level 2 Level 1 Initiative Title Department



4
2
Hire adequate staff and materials needed to complete projects for Newburgh Campus
$81,700.00 / $40,200.00
Maintenance

Assessment

DateDepartment NameStatusCost to DateFunding Source 